Sources & publication notes

Preserving the distinction between a planning scenario and a committed project.

Recovered source package

ECM_Data_Center Development_Prospectus.pptx (50 slides) and its PDF; ECM_Data_Center Development_Model.xlsx; and ECM_Data_Center_Rev_B_Decision_Model.xlsx. The nine image slides and the ECM logo were recovered from the earlier work.

All source references identify the September 9, 2026 planning versions. This website adaptation is not a fresh market, utility, legal or engineering verification.

Graphic clarifications

On the investor cover, “Secured for Growth” must not be interpreted as confirmed utility capacity. On Economics Snapshot, about $198/kW/month is the rent needed to meet the 8.50% NOI-yield hurdle, not operating break-even.
The $900 million target and 9.35% yield are unverified sensitivities. The original graphics are retained for review, with explicit notices beside them; their raster wording has not been silently altered.

Before public release

Approve the factual claims and public/private content split before uploading. Obtain appropriate securities-counsel review before using investor material in a public capital-raising campaign. A planning disclaimer is not a substitute for that review.

This preview is marked noindex. That is an indexing instruction, not access control. Confidential material requires genuine host-side authentication or an approved data room.

Link behavior

The website uses permanent section identifiers, not fragile page numbers. The preview links work within this HTML file. A host path such as /data-center/ is proposed, not published.
The review PowerPoints link internally to their detail slides. Domain-specific website links can replace those once the website address and hosting layout are confirmed.

Visual-to-detail register

Visual Planning sources Stable detail fragment
Data Center Development
Original prospectus: slides 2-4, 41-46.
Rev B model: Read_Me; Budget_Boundaries.
#project-overview
Investor Prospectus
Original prospectus: slides 2-6, 35-37, 39, 41-45.
Rev B model: Read_Me; Inputs; Gate_Register; Budget_Boundaries.
#investor-overview
Site Vision and Development Opportunity
Original prospectus: slides 7-14, 19-32, 39-40.
Rev B model: Site_Utility; Interior_BOD.
#investor-site
Economics Snapshot
Original prospectus: slides 35-38.
Original model: Capex; Operating.
Rev B model: Inputs; Yield_Cases; Budget_Boundaries.
#investor-economics
Proposed Tenant Prospectus
Original prospectus: slides 4, 10-18, 40.
Rev B model: Tenant_Terms; Inputs; IT_Plan.
#tenant-overview
Capacity and Service Framework
Rev B model: IT_Plan; Interior_BOD; Recovery.
Original prospectus: slides 10, 18.
#tenant-capacity
Designed for Scalable Tenant Operations
Rev B model: Interior_BOD; Recovery; Energy_Screen; Budget_Boundaries.
Original prospectus: slides 12-18, 40.
#tenant-operations
Construction Cost Prospectus
Original prospectus: slides 33-36.
Original model: Inputs; Capex; Funding.
Rev B model: Budget_Boundaries; Read_Me.
#construction-budget
Core Infrastructure Scope
Original prospectus: slides 12-16, 23-34, 39-40.
Rev B model: Interior_BOD; Site_Utility; Budget_Boundaries.
#construction-infrastructure