EPIC CONSTRUCTION MANAGEMENT LLC

Building today for tomorrow.

Data Center Development

One project. Three distinct perspectives.
This review package connects the investor, proposed-tenant and construction-cost presentations to the supporting detail for each visual. The working concept is a wholesale-capacity facility, not an established operating campus or a GPU-compute business.
Source basis: September 9, 2026 planning package · Not independently re-underwritten.

48 MW

Ultimate critical IT concept

24 MW

First-phase planning capacity

6 MW

Proposed delivery blocks

Planning data & boundaries

Perspective What the linked detail addresses Evidence still needed
Investor
Development thesis, site, economics, funding and risk
Site control, utility terms, tenant commitments and validated returns
Proposed tenant
Reserved capacity, density, interfaces and service requirements
Signed equipment brief, lease terms, operator and acceptance criteria
Construction cost
Cost boundaries, work packages, delivery and commissioning
Engineered scope, quantities, quotations and approved schedule

What is established

The original feasibility presentation and the Rev B decision model provide a consistent planning framework. They do not establish ownership of a parcel, allocated utility capacity, a signed tenant, financing, permits or a contractual service date.

Keep the business models separate

Facility capacity rent is the working revenue model. Tenant compute, storage, active networks and software are separate unless expressly transferred by contract. Selling GPU-compute services would require a different operating and investment model.

Keep the four cost scopes visible

Base facility, additional on-site energy, tenant IT and remote recovery are separate scopes. Solar, extended battery storage, a prime-power plant and remote recovery are not silently included in the base facility figure. Unpriced does not mean zero.

Publication status

This is an internal-review website prototype. No website has been changed or published. The graphics are conceptual illustrations, not photographs of an ECM-owned site or engineered layouts. Investor material and detailed security information require a separate publication decision.

Source trail